The “Energy Efficiency Fund” project was based on six distinct activities with underlying tasks in order to achieve its proposed purpose: to assess the energy quality of a specific group of homes, in order to operationalise not only the model but also to disseminate the practice with regard to the urgency of qualifying the degree of energy efficiency of each home. Thus, of the six activities, four refer to the promotion of the fund and two to issues related to coordination and assessment.


The methodology applied is divided into two major phases: the first, for dissemination, promotion and awareness-raising on the subject in general, followed by the implementation phase, essentially characterised by the completion of questionnaires/studies, to be applied to the universe of 500 homes in the Municipality of Sines. This was followed by a second phase, described by the preparation of individual reports on each of the homes analysed. This resulted in the preparation of a general report on the housing fabric of the Municipality of Sines.


It is important to note that the methodology adopted focused mainly on meeting the general and specific objectives proposed, in order to ensure that all indicators were achieved, with particular emphasis on the indicator of studies presented, more specifically, the presentation of 500 studies.


Project implemented by Sines Tecnopolo and promoted by Sines City Council.


Dates

2011 - 2014


Budget

205.000€


Executed Budget

205.000€


Execution Rate

100%